Project in Mount Pleasant
2 Lot Green Title Subdivision
Suburb: Mount Pleasant
Original Number of Lots: 1
Final Number of Lots: 2
Agencies involved
– City of Melville
– Water Corporation
– Western Power
Planning Conditions
(Western Australian Planning Commission 2019 )
“1. The land being filled, stabilised, drained and/or graded as required to ensure that:
(a) lots can accommodate their intended development; and
(b) finished ground levels at the boundaries of the lot(s) the subject of this approval match or otherwise coordinate with the existing and/or proposed finished ground levels of the land abutting; and
(c) stormwater is contained on-site, or appropriately treated and connected to the local drainage system. (Local Government)
2. All buildings, outbuildings and/or structures present on lots 301 and 302 at the time of subdivision approval being demolished and materials removed from the lots. (Local Government)
3. Arrangements being made with the Water Corporation so that provision of a suitable water supply service will be available to the lots shown on the approved plan of subdivision. (Water Corporation)
4. Arrangements being made with the Water Corporation so that provision of a sewerage service will be available to the lots shown on the approved plan of subdivision. (Water Corporation)
5. Arrangements being made to the satisfaction of the Western Australian Planning Commission and to the specification of Western Power for the provision of an underground electricity supply to the lot(s) shown on the approved plan of subdivision. (Western Power) ”
Key Dates
– WAPC Approval – Form 1A
issued: December 2018
received: January 2019
– Service Agreements
Water Corporation
issued: January 2019
received: January 2019
Western Power
issued: January 2019
received: February 2019
– Clearances
Water Corporation
issued: April 2019
received: April 2019
Western Power
issued: July 2019
received: July 2019
Local Government
issued: April 2019
received: May 2019
– Landgate Plan Lodgement
issued
plan: May 2019
doc’s: May 2019
received
IOFD’s: June 2019
– WAPC – Form 1C
issued: May 2019
approved: June 2019
– Landgate Registration
New Titles Created: November 2019