Project: Kardinya

Project in Kardinya

2 Lot Green Title Subdivision


Suburb: Kardinya


Original Number of Lots: 1


Final Number of Lots: 2


 

Agencies involved

– City of Melville
– Water Corporation
– Western Power

Planning Conditions

(Western Australian Planning Commission 2019 )

“1. The land being filled, stabilised, drained and/or graded as required to ensure that:

(a)  lots can accommodate their intended development; and

(b)  finished ground levels at the boundaries of the lot(s) the subject of this approval match or otherwise coordinate with the existing and/or proposed finished ground levels of the land abutting; and

(c)  stormwater is contained on-site, or appropriately treated and connected to the local drainage system. (Local Government)

2. Redundant vehicle crossover(s) to be removed and the kerbing, verge, and footpath (where relevant) reinstated with grass or landscaping to the satisfaction of the Western Australian Planning Commission and to the specifications of the local government. (Local Government)

3. Arrangements being made with a licenced water provider for the provision of a suitable water supply service to the lot(s) shown on the approved plan of subdivision. (Water Corporation)

4. Arrangements being made with the Water Corporation so that provision of a sewerage service will be available to the lots shown on the approved plan of subdivision. (Water Corporation)

5. Suitable arrangements being made with the Water Corporation for the drainage of the land either directly or indirectly into a drain under the control of that body. (Water Corporation)

6. Arrangements being made to the satisfaction of the Western Australian Planning Commission and to the specification of Western Power for the provision of an underground electricity supply to the lot(s) shown on the approved plan of subdivision. (Western Power) ”

Key Dates

– WAPC Approval – Form 1A

issued: February 2019
received: May 2019

– Service Agreements

Water Corporation

issued: May 2019
received: May 2019

Western Power

issued: May 2019
received: June 2019

– Clearances

Water Corporation

issued: August 2019
received: August 2019

Western Power

issued: July 2019
received: July 2019

Local Government

issued: August 2019
received: September 2019

– Landgate Plan Lodgement

issued
plan: July 2019
doc’s: September 2019

received
IOFD’s: October 2019

– WAPC – Form 1C

issued: September 2019
approved: October 2019

– Landgate Registration

New Titles Created: January 2020