Project in Palmyra
2 Lot & Common Property Survey-Strata Subdivision
Suburb: Palmyra
Original Number of Lots: 1
Final Number of Plots: 2 plus Common Property
Agencies involved
– City of Melville
– Water Corporation
– Western Power
Planning Conditions
(Western Australian Planning Commission 2019 )
“1. Other than buildings, outbuildings and/or structures shown on the approved plan for retention, all buildings, outbuildings and/or structures present on Lots 2 and common property (CP3) at the time of subdivision approval being demolished and materials removed from the lots. (Local Government)
2. The existing dwelling being retained is to comply with the requirements of the Residential Design Codes. (Local Government)
3. The land being filled, stabilised, drained and/or graded as required to ensure that:
(a) lots can accommodate their intended development; and
(b) finished ground levels at the boundaries of the lot(s) the subject of this approval match or otherwise coordinate with the existing and/or proposed finished ground levels of the land abutting; and
(c) stormwater is contained on-site, or appropriately treated and connected to the local drainage system. (Local Government)
4. A 4.24 metre truncation is to be provided at the junction of the access way and the proposed rear lot. (Local Government)
5. The access way to the rear lot shall be a minimum width of 3.0 metres, free of any building projections associated with existing site development and depicted on the survey strata plan accordingly. (Local Government)
6. Arrangements being made with a licenced water provider for the provision of a suitable water supply service to the lot(s) shown on the approved plan of subdivision. (Water Corporation)
7. Arrangements being made with the Water Corporation so that provision of a sewerage service will be available to the lots shown on the approved plan of subdivision. (Water Corporation)
8. Arrangements being made to the satisfaction of the Western Australian Planning Commission and to the specification of Western Power for the provision of an electricity supply to the survey-strata lots shown on the approved plan of subdivision, which may include the provision of necessary service access rights either as an easement under Section 136C and Schedule 9A of the Transfer of Land Act 1893 for the transmission of electricity by underground cable, or (in the case of approvals containing common property) via a portion of the common property suitable for consumer mains. (Western Power)“
Key Dates
– WAPC Approval – Form 1A
issued: May 2019
received: June 2019
– Service Agreements
Water Corporation
issued: June 2019
received: June 2019
Western Power
issued: July 2019
received: July 2019
– Clearances
Water Corporation
issued: October 2019
received: October 2019
Western Power
issued: November 2019
received: November 2019
Local Government
issued: November 2019
received: December 2019
– Landgate Plan Lodgement
issued
plan: November 2019
doc’s: November 2019
received
IOFD’s: January 2020
– WAPC – Form 1C
issued: January 2020
approved: January 2020
– Landgate Registration
New Titles Created: March 2020