Project: Edgewater

Project in Edgewater

2 Lot & Common Property Survey-Strata Subdivision


Suburb: Edgewater


Original Number of Lots: 1


Final Number of Lots: 2 plus Common Property


 

Agencies involved

– City of Joondalup
– Water Corporation
– Western Power

Planning Conditions

(Western Australian Planning Commission 2018)

“1. All buildings having the necessary clearance from the new boundaries as required under the relevant legislation including the Local Planning Scheme, Building Act 2011, and National Construction Code Series/Building Code of Australia (as amended). (Local Government)

2. Other than buildings, outbuildings and/or structures shown on the approved plan for retention, all buildings, outbuildings and/or structures present on Lots 2 and CP3 at the time of subdivision approval being demolished and materials removed from the lot(s). (Local Government)

3. The existing dwelling being retained is to comply with the requirements of the Residential Design Codes. (Local Government)

4. The land being filled, stabilised, drained and/or graded as required to ensure that:

(a)  lots can accommodate their intended development;

(b)  finished ground levels at the boundaries of the lot(s) the subject of this approval match or otherwise coordinate with the existing and/or proposed finished ground levels of the land abutting; and

(c)  stormwater is contained on-site, or appropriately treated and connected to the local drainage system. (Local Government)

5. A 1.5 metre x 1.5 metre truncation is to be provided at the junction of the access way and the Settler Way road reserve. (Local Government)

6. Suitable arrangements being made with the local government for the provision of vehicular crossover(s) to service the lot(s) shown on the approved plan of subdivision. (Local Government)

7. Redundant vehicle crossover(s) to be removed and the kerbing, verge, and footpath (where relevant) reinstated with grass or landscaping to the satisfaction of the Western Australian Planning Commission and to the specifications of the local government. (Local Government)

8. Arrangements being made to the satisfaction of the Western Australian Planning Commission and to the specification of Western Power for the provision of an electricity supply to the survey strata lots shown on the approved plan of subdivision, which may include the provision of necessary service access rights either as an easement under Section 136C and Schedule 9A of the Transfer of Land Act 1893 for the transmission of electricity by underground cable, or (in the case of approvals containing common property) via a portion of the common property suitable for consumer mains. (Western Power)

9. Arrangements being made with the Water Corporation so that provision of a suitable water supply service will be available to the lots shown on the approved plan of subdivision. (Water Corporation)

10. Arrangements being made with the Water Corporation so that provision of a sewerage service will be available to the lots shown on the approved plan of subdivision. (Water Corporation)”

Key Dates

– WAPC Approval – Form 1A

issued: March 2018
received: July 2018

– Service Agreements

Water Corporation

issued: July 2018
received: July 2018

Western Power

issued: July 2018
received: July 2018

– Clearances

Water Corporation

issued: October 2018
received: October 2018

Western Power

issued: February 2019
received: March 2019

Local Government

issued: October 2018
received: February 2019

– Landgate Plan Lodgement

issued
plan: February 2019

received
IOFD’s: March 2019

– WAPC – Form 1C

issued: March 2019
approved: March 2019

– Landgate Registration

New Titles Created: May 2019